Equipment

Concrete pile driller

Concrete pile driller

Concrete pile drilling attachment with excavator

Concrete pile drilling attachment is specially desinged to remove old contrete pile by drilling and cutting it.

The equipment consists of main bucket and casing tubes to prevent hole-collapsed. After casing tube is installed, you prepare for excavation by attaching a bucket equipped with a concrete cutter on auger drive.

The hydraulic power will be supplied from your pile driver. And drill bucket is rotating and drillling into the hole to cut off contrete pile.

After the first concrete is out an extension rod is installed to reach out the second concrete pile.

The concrete removal sequence is as described above, and the concrete is removed through repeated operations depending on the depth to be removed.

This equipment can cut out old pile without digging into the extire area. Saving time and cost for rebuilding project

  • No digging groud
  • Fast working speed and saving cost
  • Power soruce from excavator
  • Quality drill teeth and cutter
  • Customerized design and size

Specification

Model MS 300T MS 650T MS 850T
Drill dia. Ø300 Ø650 Ø850
Lenght of drilling 6~7m 9m 9~10m
Bucket size Ø650×2.5m Ø650×2.5m Ø800×2.5m
Bucket clamp Hyd. type Hyd. type Hyd. type
Extension rod 2.3m×3 2.3m×3 2.3m×3
Drill dia. Ø900 Ø900 Ø100
Specification

Process sequence for concrete pile drilling

Process sequence for concrete pile drilling

Drill bucket

Drill bucket

Drill bucket

Commissioning

  • Installation of casing
    Installation of casing
  • Holding casing
    Holding casing
  • Take pile away
    Main bucket
  • Bukect inside
    Drilling
  • Wired controller
    Take pile away
  • Wireless controller
    Bukect inside
  • Cable reel cart
    Drop off pile
  • Cable reel cart
    Cutted pile